USACE expands emergency response in Ocean Shores as coastal flooding threat continues

USACE provides PL 84-99 assistance in Ocean Shores Emergency repair work is underway at the Ocean Shores breakwater, Nov. 22, 2026. The U.S. Army Corps of Engineers, Seattle District, is providing direct assistance to the City of Ocean Shores under Public Law 84-99, Emergency Response to Natural Disasters, to support repairs that help reduce overtopping from large waves and prevent saltwater from entering freshwater canals amid coastal flooding risk associated with king tides and storm surge. (U.S. Army photo by Travis England) (Travis England/U.S. Army Corps of Engineers, Se)

OCEAN SHORES, Wash — The U.S. Army Corps of Engineers is continuing emergency operations along Washington’s coast as communities face an ongoing risk of coastal flooding linked to king tides and storm surge conditions.

The Seattle District of the U.S. Army Corps of Engineers said it has mobilized emergency responders and resources to assist communities affected by coastal flooding that began impacting the region earlier this month.

“This week, we mobilized responders to assist various communities impacted by the coastal flooding conditions that began occurring across the region in early November,” said Krystle Walker, emergency management chief for the Seattle District. “We’re conducting emergency repairs and providing flood-fighting materials along the coast of Washington alongside local and tribal partners.”

The agency is operating under its emergency flood response authority, known as Public Law 84-99, which allows the Corps to provide assistance to state and local governments before, during, and after flood events.

In Ocean Shores, crews are carrying out emergency repairs to a marina breakwater in an effort to prevent large waves from overtopping the structure. The Corps is also reinforcing water system infrastructure near Discovery Avenue Southwest and providing materials to help prevent saltwater from entering the city’s freshwater canal system.

For several days, federal emergency-management personnel have worked alongside city officials to strengthen coastal protections as severe wave conditions continue to affect the area. Officials say the work has made significant progress in reducing flood risks and protecting critical infrastructure.

The Corps emphasized that the emergency repairs currently underway in Ocean Shores are separate from its ongoing North Jetty rehabilitation project.

According to the agency, the North Jetty work is focused on restoring deteriorated sections of the navigation structure to prevent sediment buildup in Grays Harbor. The project was originally authorized in 1895 as part of the federal navigation project and is intended to support maritime navigation, not flood protection.

Residents are encouraged to remain vigilant, monitor local weather and coastal conditions, and follow guidance from local emergency officials as king tides and storm-driven waves continue to impact the Washington coast.